Showing 1–3 of 3

Q1.Bid evaluation must be made against:

Medium
A The criteria stated in the bidding documents
B New criteria after opening
C Personal preference
D A media survey
Contract Award PPSC 2024

Correct Answer: A

Changing criteria after bid opening undermines fairness and transparency.

Q2.The successful bidder is generally the one whose bid is:

Medium
A Responsive and evaluated according to the stated criteria
B The most expensive without review
C Submitted after the deadline
D Missing required documents
Contract Award PPSC 2024

Correct Answer: A

Award follows responsiveness and evaluation under the stated criteria.

Q3.A contract should be awarded only after:

Easy
A Required evaluation and approval
B A verbal suggestion
C A supplier’s advertisement
D The contract is completed
Contract Award PPSC 2024

Correct Answer: A

Award follows evaluation and the required approval process.